The Vistula Spit canal four years on: who really uses it and what next for Elbląg

The canal across the Vistula Spit has been open since September 2022. The latest figures show it is used mainly by yachts, while cargo ships can be counted on one hand. We look at the numbers and at when large ships are due to reach Elbląg.

Jan Korczyński

5 min read
ShareX
Sailing yachts moored at a wooden jetty
Photo: Stock Birken / Unsplash

In short

  • By the end of August 2026, 1,249 vessels had passed through the canal, 1,024 of them yachts and motorboats and only 3 cargo ships.
  • 2024 was the record year with 1,909 passages. In 2025 there were 1,304.
  • The Elbląg river is being dredged to 5 m along 7.45 km. The contract is worth 51 million zł and is due to finish by February 2027 at the latest.
  • The full upgrade of access to Elbląg port, worth about 2.3 billion zł, is due to run until 2028, with terminal expansion until 2029.
  • For visitors, the biggest change is the swing bridges, where road traffic sometimes stops.

On 17 September 2022 a shipping canal opened across the Vistula Spit between Skowronki and Przebrno. For the first time since the Middle Ages, ships can sail from the Vistula Lagoon to the Baltic without entering Russian waters. Four years on, there is plenty of data on who uses the canal. The answer is simple: mostly sailors.

The canal in numbers

1,249

vessels passed through by the end of August 2026

1,024

of them yachts and motorboats

3

cargo ships carrying freight in the same period

1,909

passages in the record year 2024

Type of vesselNumber (to end of August 2026)
Recreational (yachts, motorboats)1,024
Commercial without cargo (mostly barges working on the fairway)106
State vessels (Maritime Office, police, Border Guard)105
Fishing11
Commercial with cargo3
Total1,249
Figures reported by WNP.pl and Interia, citing Dziennik Bałtycki, September 2026.

Traffic clearly follows the sailing season. In May 2026, 140 vessels passed through, in June 269, and in August, the busiest month, 353. Traffic drops in autumn. In 2026, 33 vessels under foreign flags also used the canal, mostly German, plus Swedish, Norwegian and Dutch.

YearPassages
20231,589
20241,909 (record)
20251,304
2026 (to end of August)1,249

Why so few cargo ships

The canal was meant above all to open the port of Elbląg to seagoing ships up to 100 m long, 20 m wide and with a 4 m draught. But the cut itself is only the first stretch of the route. For such a ship to reach Elbląg, it needs a deep enough fairway across the shallow lagoon and up the Elbląg river, plus quays and terminals in the port to handle cargo. That work is still under way.

What is happening on the Elbląg river

In July 2026 a contract was signed for the second part of the dredging on the Elbląg river. It is worth 51 million zł and covers about 7.45 km of fairway, from the Vistula Lagoon to a point near the outflow of the Elbląg wastewater treatment plant. The fairway is to be 5 m deep. According to the Maritime Office in Gdynia, the work should finish around the turn of 2026 and 2027, by February 2027 at the latest. As of July about half of the dredging had been done, with the spoil placed on an artificial island in the lagoon.

The final stretch, about 3 km long, is still in preparation. It is to be 36 m wide and 5 m deep, with a 160 m turning basin where larger ships can turn around. The project has its environmental decision, and the next steps are a water-law permit and a building permit.

StagePlanned date
Dredging 7.45 km of the Elbląg river to 5 mturn of 2026/2027, February 2027 at the latest
Larger ships entering Elblągannounced for the first half of 2027, not certain
Final fairway section and turning basin2028
Expansion of Elbląg port terminalsuntil 2029
Based on Radio Gdańsk, Interia and Express Elbląg (July-October 2026).

The whole programme to improve access to Elbląg port is expected to cost about 2.3 billion zł. The national government is responsible for the waterway from the sea and the city of Elbląg for port infrastructure. Modernising terminal T2 alone costs over 224 million zł. The cut across the Spit, with a canal about 1.5 km long, a lock and two swing bridges, cost about 2 billion zł.

What the canal changes for visitors

  • Swing bridges. The road along the Spit crosses the canal on swing bridges. When a vessel passes, the bridge opens and traffic stops. In summer, when most yachts pass, allow extra time if you are heading to Krynica Morska to catch a boat.
  • A new sight. There is a viewing point by the canal with a good view of the lock and passing vessels. Children often find it more exciting than the beach.
  • More sailors. The canal cuts about 100 km off the route from the lagoon to the Baltic. Sailors from Elbląg, Frombork and Tolkmicko reach the gulf faster, and yachts from Gdańsk can enter the lagoon more easily.

What it means for restaurants on the Spit

More than a thousand yachts a season means more than a thousand crews who moor somewhere and eat somewhere. For restaurants in Krynica Morska, Kąty Rybackie or Piaski they are a distinct group of guests: they arrive at irregular hours and often want to order food before they come ashore. A simple way to order online with a set pickup time can make a real difference here.

Sailors order from their phones

With Dinevo, guests can order takeaway for pickup at a set time, and you pay no commission on orders.

See online ordering

Places in this article

Frequently asked questions

How many ships have used the Vistula Spit canal?

By the end of August 2026, 1,249 vessels, including 1,024 yachts and motorboats and 3 cargo ships. The record year 2024 saw 1,909 passages, and 2025 saw 1,304.

When will large ships reach Elbląg?

Dredging the Elbląg river to 5 m is due to finish by February 2027 at the latest. Larger ships were announced for the first half of 2027, but the date is not certain. The final fairway section with a turning basin is planned for 2028, and terminal expansion will run until 2029.

How much did the Vistula Spit canal cost?

The canal itself cost about 2 billion zł. The whole programme to improve access to Elbląg port is estimated at about 2.3 billion zł.

Is the bridge over the canal sometimes closed?

Yes. The road crosses on swing bridges that open when a vessel passes. Cars and bikes then wait for a quarter of an hour or so.

What size ships can use the canal?

The canal was designed for vessels up to 100 m long, 20 m wide and with a 4 m draught.

Sources

The figures and conclusions in this article come from the publications below.

  1. Four years of the Vistula Spit canal: statistics show who uses it (in Polish). WNP.pl, 2026
  2. The Vistula Spit canal after four years: cargo barely moves (in Polish). Interia Biznes, 2026
  3. 51 million zł to dredge the Elbląg river (in Polish). Radio Gdańsk, 2026
  4. Larger ships in Elbląg in 2027? Dates announced (in Polish). Express Elbląg, 2026
  5. Contract signed for the second part of dredging on the Elbląg river (in Polish). IntermodalNews, 2026
  6. Vistula Spit canal. Wikipedia
TagsVistula SpitVistula Spit canalshipping canalElblągVistula LagoonnewsPoland

About the author

Jan Korczyński

Dinevo blog author

Writes for the Dinevo blog about what can be checked in data and research: sales, menus and guest behaviour.